Our Projects

Strip Out Works Aldi

Demolition and Associated Works at:

Our Projects

Project Overview

Prinical Contractor        AR Demolition Ltd
Volume of Site 18,000m2
Volume of Waste 1585.74 Tonnes

Key Work Activities

Soft strip, removal of all internal buildings, removal of all external walls &  cladding.

Removal of box profile roof, grub up the loading bay and tarmac road. To leave all live services in place and protect from weather, to leave concrete structure/frame work in place. Finally finishing with  removal of wind bracing and vertical supports.

Slide 1

Slide 2

Project Description

AR Demolition Ltd were instructed to carry out works including  the removal  of all existing  concrete hard-standing areas. The complete soft strip for all the structures was required to leave only the skeleton frame.

Key Challenges

Working around live services. Short timescale to deliver project and confined area of working space.

Key H,S&E Risks

Key Work Activities:  Soft strip, removal of all internal buildings, removal of all external walls &  cladding. Removal of box profile roof, grub up the loading bay and tarmac road. To leave all live services in place and protect from weather, to leave concrete structure/frame work in place. Finally finishing with  removal of wind bracing and vertical supports.

Equipment Used 

Scissor lifts, Bobcat, Tower scaffolds, 360 Excavator on shear, bucket and hammer, Gas operated tile lifter, Cherry pickers & various hand tools.

Works were conducted within close proximity to local  community, including businesses.Traffic management was required  and measures put in place to deal with the project without any delays occurring.

The Project was completed on time and on schedule. To the complete satisfaction of the client. 

More case studies of interest...

Back to case studies

Latest News

Added 14/10/2019

Willmott Dixon Partner Awards -

AR Demolition Ltd were thrilled to receive Highly Commended in the 'All Safe' category at the Midlands Willmott Dixon Partner Awards 
Michael Henderson Director of QHS&E was there to receive the award on the 3rd of October 2019 at Birmingham Town Hall. 

Read More
Added 26/06/2019

Institute of Demolition Engineers Vice President

In November 2018 Richard Dolman became the IDE Vice President 
"I want to use my new position to help address the skills shortage, inspire a new generation of demolition engineers, to promote ideals throughout our connected sectors and promote safer ways of working in our industry."
 

Read More
Added 17/06/2019

Construction News Awards

AR DEMOLITION SHORTLISTED FOR MAJOR INDUSTRY AWARD

Read More
More News