Our Projects

Enabling Works at Acton Refinery


Our Projects

Project Overview

Principle Contractor:       AR Deconstruction & Demolition

Volume of waste recycled:           70%

 

Key Work Activities:

  • Decommissioning and deconstruction of a former precious metals refinery based in Acton, West London for VALE Europe.
  • The refinery, associated ancillary buildings were deconstructed along with a partial de-commissioning of the former administration building and removal of underground fuel tanks and an air raid shelter.

Project Description:

We deconstructed a former precious metals refinery in Acton, West London involving the partial de-commissioning of the administration building, extraction of stone features and removal of underground structures for VALE Europe.

This extensive project was completed during the Covid-19 pandemic and therefore a satellite compound with living facilities was created for the workforce who could safely isolate in the facilities during the week. We are committed to safety and therefore we extended our Covid safe site by installing automatic gates, hands-free temperature scanners and the latest faeces Covid scanning system. This resulted in a Covid transmission rate of zero.

The site remained live throughout the project so we ensured live services were protected throughout the enabling works.

The initial phase of the project was to strategically approach the containment and removal all remaining hazardous material from this former refinery of precious metals. All personnel working or visiting the site were also tested for platinum salts.

Works then commenced on the removal of reconstituted stone features from the roof and side elevations of the administration building whilst maintaining the main structural integrity of the building.

Soft and hard strip to the offices, laboratory and stores were completed followed by the removal of underground fuel tanks and an air raid shelter. The deconstruction of the chimneys, tanks and vessels were then undertaken. Finally cut and fill of a section of ground ensured the site was finished to a standard allowing for future use.

 

Key Health and Safety Risks:

The greatest risks were to personnel during the removal of the hazardous materials and ensuring they were also protected during the pandemic whilst completing a complex demolition project in West London on a live site.

High standards of control were also required over noise, dust and vibration due to the site’s location within the capital city.

This project met the stringent environmental standards, kept all staff safe during the pandemic and was successfully completed to programme.

More case studies of interest...

Back to case studies

Latest News

Added 23/11/2023

Safety innovation for the benefit of the demolition industry

Innovating to improve safety for the demolition industry

Read More
Added 12/09/2023

CN Specialists Award Winner

Awarded Demolition Specialist of the Year, for the second consecutive year, at the 2023 Construction News Specialists Awards.

Read More
Added 03/08/2023

Construction News Award Winner

AR, The Enabling Partner, has won Supply Chain Excellence at the 2023 Construction News Awards.

Read More
More News