Deconstruction GE Cardiff Test Cells

GE Cardiff, Caerphilly Road, Nantgarw, Cardiff CF15 7YJ

Our Projects

Project Overview

Principal Contractor        AR Demolition Ltd
Volume of Site 3,702.71 m²
Volume of Waste 99.65% Recycled

Key Work Activities

  • Demolition of test cells, workshops, and offices, as well as tanks and associated infrastructure.
  • Removal of licensed and non- licensed asbestos including de-sheeting of AC roof panels.
  • All works were to be undertaken with minimal disruption to GE operations which will remain live directly adjacent to the site throughout the project.

 

Project Description:

It was recognised from the early offset that the project was required to be undertaken with due regard to the sensitivity of the GE operations.

AR's Aim was to deliver the project with minimal impact to the live operations directly adjacent to the site. With nature and risks associated with the GE operations, environmental emissions and all normal aspects of demolition projects (such as waste movements, dust & vibration) were going to need robust controls.

Daily communication with the client and daily site briefings/toolbox talks with all AR demolition operatives and letter drops to residents were undertaken.

Key Challenges:

With the unique and sensitive nature of the surrounding operations and the sensitivity over dust emissions, AR's new innovative high reach dust suppression equipment paid dividends. The new equipment successfully controlled the dust throughout a series of significant mechanical demolition activities. This resulted in the delivery of the project with no adverse elevations in dust levels.

Key Health and Safety Risks:

  • Working within the Live GE facility and in close proximity to live structures
  • Access and egress constraints
  • The sensitivity of adjacent Live Operations to FOD, Noise, Dust & Vibration
  • Access / egress constraints
  • Asbestos Cement Roof Removal

 

The project was completed in 18 weeks, 5,000 hours worked and zero injuries sustained to the complete satisfaction of the client.

More case studies of interest...

Back to case studies

Latest News

Added 23/11/2023

Safety innovation for the benefit of the demolition industry

Innovating to improve safety for the demolition industry

Read More
Added 12/09/2023

CN Specialists Award Winner

Awarded Demolition Specialist of the Year, for the second consecutive year, at the 2023 Construction News Specialists Awards.

Read More
Added 03/08/2023

Construction News Award Winner

AR, The Enabling Partner, has won Supply Chain Excellence at the 2023 Construction News Awards.

Read More
More News